Films Why AI companies are moving into the power business
Why AI companies are moving into the power business

In two sentences
Some AI companies now sit beside turbines, sign twenty-year power contracts, or buy the companies that build power plants. This film follows real arrangements, from Mississippi to Louisiana, to show what "their own power" usually means: who owns the plant, who pays for it, and who controls when the electricity arrives.
Chapters
What we know and what we don'tWhat we know
Established
MZX Tech LLC, a subsidiary within SpaceX's AI business, holds Mississippi's construction permit for a Southaven project that the AI division, now publicly branded SpaceXSI, describes as a 1.2 GW permanent power plant with 41 turbines under construction.
Mississippi Department of Environmental Quality: Southaven permit, corporate structure, and temporary-turbine record (opens the source) ↗ · SpaceXAI: SpaceXAI Greater Memphis Area update (opens the source) ↗ · SpaceX SEC filing and SpaceXSI legal/site materials: SpaceX AI-segment corporate and public-brand refresh (opens the source) ↗
Google has moved into direct energy development by acquiring Intersect, including multiple gigawatts of co-located projects in development or construction.
Intersect: Intersect current solutions and acquisition status (opens the source) ↗ · Alphabet SEC filing and Intersect/IPX transaction records: Alphabet/Intersect acquisition and IPX asset boundary (opens the source) ↗
Microsoft's 20-year PPA supports Constellation's proposed restart of the 835 MW Crane reactor.
Constellation and US Nuclear Regulatory Commission: Microsoft/Constellation Crane restart (opens the source) ↗ · US Nuclear Regulatory Commission: Current status refresh for planned nuclear examples (opens the source) ↗
Uncertain or limited
The permit authorizes construction; it is not proof that the permanent turbines are operating. The public record reviewed does not establish legal title to each turbine or the complete financing structure.
The brand refresh does not change the MDEQ permittee, which remains MZX Tech LLC. It also does not establish turbine-level title, permanent-plant operation, or compliance progress beyond what the company and regulator records specifically report.
Forecast with substantial uncertainty. On-site gas is described as emerging, not necessarily faster at scale.
International Energy Agency, Key Questions on Energy and AI (opens the source) ↗
Amazon is financing X-energy and enabling a 320 MW first phase with Energy Northwest, but Energy Northwest is to construct, own, and operate the reactors.
US Nuclear Regulatory Commission: Current status refresh for planned nuclear examples (opens the source) ↗ · Amazon: Amazon/X-energy/Energy Northwest (opens the source) ↗
Power-plant co-location does not necessarily mean common ownership or permanent behind-the-meter service.
US Federal Energy Regulatory Commission and federal court filing: Amazon/Talen Susquehanna co-location record (opens the source) ↗ · Talen Energy: Talen SEC confirmation of the Susquehanna front-of-meter transition (opens the source) ↗
AI/data-center expansion increasingly collides with slower grid connections and energy-infrastructure development.
International Energy Agency: Key Questions on Energy and AI (opens the source) ↗
Electricity use by data centers is rising rapidly in the United States and globally, with AI-focused facilities a major driver.
US Department of Energy / Lawrence Berkeley National Laboratory: US Data Center Energy Usage Report: 2025 Update (opens the source) ↗ · International Energy Agency: Key Questions on Energy and AI (opens the source) ↗
Large-load utility tariffs and negotiated service agreements can allocate generation, transmission, interconnection, minimum-payment, exit, and stranded-asset risk differently between the large customer and other ratepayers.
Louisiana Public Service Commission: LPSC final Meta/Entergy order and customer-protection terms (opens the source) ↗ · US Department of Energy / Lawrence Berkeley National Laboratory: DOE large-load rate design and integrated-resource-planning framework (opens the source) ↗
Long-term PPAs, offtake rights, equity investment, and development funding can improve project financeability by reallocating revenue and development risk, but do not guarantee completion or remove schedule, technology, fuel, construction, and regulatory risk.
Entergy's first approved Meta-related Louisiana package contains three combined-cycle plants totaling about 2,260 MW; Entergy later announced plans for seven additional plants totaling more than 5,200 MW under a separate expansion agreement. Meta does not own the plants.
Louisiana Public Service Commission: LPSC final Meta/Entergy order and customer-protection terms (opens the source) ↗ · Entergy Louisiana: Entergy/Meta Richland Parish generation (opens the source) ↗ · Entergy Louisiana: Entergy/Meta second Louisiana infrastructure announcement (opens the source) ↗
On-site generation can reduce dependence on grid-delivery timing while creating or reallocating capital, permitting, emissions, fuel, redundancy, operating, and community-impact obligations among the site and its project partners.
Mississippi Department of Environmental Quality: Southaven permit, corporate structure, and temporary-turbine record (opens the source) ↗ · New Mexico Environment Department and Supreme Court of New Mexico: Project Jupiter New Mexico permit and court record (opens the source) ↗ · US Department of Energy and US Environmental Protection Agency: DOE and EPA framework for onsite generation and microgrids (opens the source) ↗
Oracle's Project Jupiter plans a behind-the-meter fuel-cell microgrid of up to 2.45 GW, with Oracle paying the project's energy costs.
New Mexico Environment Department and Supreme Court of New Mexico: Project Jupiter New Mexico permit and court record (opens the source) ↗ · Oracle: Oracle Project Jupiter fuel-cell plan (opens the source) ↗
IPX Power received a portion of Intersect's operating and development assets.
Intersect, Intersect current solutions and acquisition status (opens the source) ↗
The cited sources do not conclusively establish Oracle's legal ownership of the generation assets.
Oracle, Oracle Project Jupiter fuel-cell plan (opens the source) ↗
Capacity serves the broader utility system as well as the large-load rationale; the approved protections do not establish zero residual ratepayer risk.
Entergy Louisiana, Entergy/Meta Richland Parish generation (opens the source) ↗
Constellation owns/operates the plant. The agreement does not establish a dedicated physical wire to Meta.
Meta, Meta/Constellation Clinton agreement (opens the source) ↗
Future project and schedule; not Google ownership.
Potential sites and development goal, not licensed, constructed, or operating plants.
Google, Google/Elementl Power site development (opens the source) ↗
The headline total of up to 6.6 GW combines existing, expanded, and future capacity with different owners, commercial structures, and dates.
Meta, Meta nuclear agreements with Vistra, TerraPower, and Oklo (opens the source) ↗
Talen/Susquehanna, not Amazon, owns the nuclear generation. The filing establishes the commercial/meter transition, not a dedicated private wire or Amazon ownership of the plant.
No final permit appears in the regulator record reviewed on 2026-10-17. Oracle's later design refinements remain proposals within a pending process.
The order documents protections; it does not prove that all residual risk to other customers is zero. Several commercial documents are redacted or confidential.
This is a general framework, not a finding about Meta, Entergy, or any single tariff.
Obligations depend on technology, operating mode, fuel, location, and permit.
A PPA may be physical or financial and does not necessarily deliver identifiable electrons. Neither a PPA nor equity funding guarantees permitting, financing close, construction, technology performance, fuel supply, schedule, or operation. Risk allocation is contract-specific and many commercial terms remain confidential.
Groundbreaking, design work, funding, licensing, construction, and commercial operation are distinct stages.
Scenario model, not a guaranteed demand outcome. It covers all data centers, not AI alone.
The announcement is evidence of Entergy's plan, not evidence that all seven later plants have regulatory approval, have begun construction, or will be completed. The protections and rate-recovery findings extracted from Order U-37425 apply to the first approved package and may not be generalized to the later proposal without its own final regulator record.
Entergy Louisiana, Entergy/Meta second Louisiana infrastructure announcement (opens the source) ↗
Our conclusion from the sources
The common strategic objective across these different arrangements is greater control over time-to-power.
Sources, by chapter
“In Southaven, Mississippi, SpaceX's AI division—now branded SpaceXSI—says it is building something that looks nothing like AI.”
As checked: MZX Tech LLC, a subsidiary within SpaceX's AI business, holds Mississippi's construction permit for a Southaven project that the AI division, now publicly branded SpaceXSI, describes as a 1.2 GW permanent power plant with 41 turbines under construction.
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- CompanySpaceXAI Greater Memphis Area updateSpaceXAI · 30 Jul 2026 (opens the source)
- CompanySpaceX AI-segment corporate and public-brand refreshSpaceX SEC filing and SpaceXSI legal/site materials · current through 17 Oct 2026 (opens the source)
Our conclusion from the sources
“And it is not alone.”
As checked: The common strategic objective across these different arrangements is greater control over time-to-power.
- RegulatorMicrosoft/Constellation Crane restartConstellation and US Nuclear Regulatory Commission · 2024-2026 (opens the source)
- RegulatorAmazon/Talen Susquehanna co-location recordUS Federal Energy Regulatory Commission and federal court filing · 2024-2025 (opens the source)
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- RegulatorProject Jupiter New Mexico permit and court recordNew Mexico Environment Department and Supreme Court of New Mexico · current through 17 Oct 2026 (opens the source)
- RegulatorLPSC final Meta/Entergy order and customer-protection termsLouisiana Public Service Commission · Order U-37425 decided 20 Aug 2025 (opens the source)
- RegulatorDOE and EPA framework for onsite generation and microgridsUS Department of Energy and US Environmental Protection Agency · current through 2026 (opens the source)
- RegulatorCurrent status refresh for planned nuclear examplesUS Nuclear Regulatory Commission · Energy Northwest, Amazon, and Kairos Power, current through 17 Oct 2026 (opens the source)
- FilingTalen SEC confirmation of the Susquehanna front-of-meter transitionTalen Energy · Form 10-Q filed with the US Securities and Exchange Commission, 2026 (opens the source)
- ResearchKey Questions on Energy and AIInternational Energy Agency · 2026 (opens the source)
- ResearchDOE large-load rate design and integrated-resource-planning frameworkUS Department of Energy / Lawrence Berkeley National Laboratory · 2024-2025 (opens the source)
- CompanyIntersect current solutions and acquisition statusIntersect · current through 2026 (opens the source)
- CompanySpaceXAI Greater Memphis Area updateSpaceXAI · 30 Jul 2026 (opens the source)
- CompanyOracle Project Jupiter fuel-cell planOracle · 27 Apr 2026 through 15 Oct 2026 (opens the source)
- CompanyEntergy/Meta Richland Parish generationEntergy Louisiana · 6 Dec 2024 and 20 Aug 2025; Entergy 2025 Performance Report published 2026 (opens the source)
- CompanyMeta/Constellation Clinton agreementMeta · 3 Jun 2025 (opens the source)
- CompanyGoogle/Kairos/TVA Hermes 2Google · 18 Aug 2025 (opens the source)
- CompanyAmazon/X-energy/Energy NorthwestAmazon · 16 Oct 2024 with later updates (opens the source)
- CompanyGoogle/Elementl Power site developmentGoogle · 7 May 2025 (opens the source)
- CompanyMeta nuclear agreements with Vistra, TerraPower, and OkloMeta · 9 Jan 2026 (opens the source)
- CompanyAlphabet/Intersect acquisition and IPX asset boundaryAlphabet SEC filing and Intersect/IPX transaction records · 2026 (opens the source)
- SourcePPA and project-finance risk frameworkUS Department of Energy and National Renewable Energy Laboratory · 2024-current (opens the source)
“Technology companies are signing decades-long power contracts, financing reactors, placing data centers beside power stations, and even buying energy developers.”
As checked: Google has moved into direct energy development by acquiring Intersect, including multiple gigawatts of co-located projects in development or construction.
“Technology companies are signing decades-long power contracts, financing reactors, placing data centers beside power stations, and even buying energy developers.”
As checked: Microsoft's 20-year PPA supports Constellation's proposed restart of the 835 MW Crane reactor.
- RegulatorMicrosoft/Constellation Crane restartConstellation and US Nuclear Regulatory Commission · 2024-2026 (opens the source)
- RegulatorCurrent status refresh for planned nuclear examplesUS Nuclear Regulatory Commission · Energy Northwest, Amazon, and Kairos Power, current through 17 Oct 2026 (opens the source)
“Technology companies are signing decades-long power contracts, financing reactors, placing data centers beside power stations, and even buying energy developers.”
As checked: Amazon is financing X-energy and enabling a 320 MW first phase with Energy Northwest, but Energy Northwest is to construct, own, and operate the reactors.
“Technology companies are signing decades-long power contracts, financing reactors, placing data centers beside power stations, and even buying energy developers.”
As checked: Power-plant co-location does not necessarily mean common ownership or permanent behind-the-meter service.
- RegulatorAmazon/Talen Susquehanna co-location recordUS Federal Energy Regulatory Commission and federal court filing · 2024-2025 (opens the source)
- FilingTalen SEC confirmation of the Susquehanna front-of-meter transitionTalen Energy · Form 10-Q filed with the US Securities and Exchange Commission, 2026 (opens the source)
“Because the best computer in the world is still useless if its power arrives years late.”
As checked: AI/data-center expansion increasingly collides with slower grid connections and energy-infrastructure development.
“US data centers used about 192 terawatt-hours of electricity in 2024. In the Department of Energy's reference case, that rises to 649 terawatt-hours by 2030.”
As checked: Electricity use by data centers is rising rapidly in the United States and globally, with AI-focused facilities a major driver.
Also used in this chapter
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- RegulatorMicrosoft/Constellation Crane restartConstellation and US Nuclear Regulatory Commission · 2024-2026 (opens the source)
- RegulatorAmazon/Talen Susquehanna co-location recordUS Federal Energy Regulatory Commission and federal court filing · 2024-2025 (opens the source)
- RegulatorProject Jupiter New Mexico permit and court recordNew Mexico Environment Department and Supreme Court of New Mexico · current through 17 Oct 2026 (opens the source)
- RegulatorLPSC final Meta/Entergy order and customer-protection termsLouisiana Public Service Commission · Order U-37425 decided 20 Aug 2025 (opens the source)
- RegulatorDOE and EPA framework for onsite generation and microgridsUS Department of Energy and US Environmental Protection Agency · current through 2026 (opens the source)
- RegulatorCurrent status refresh for planned nuclear examplesUS Nuclear Regulatory Commission · Energy Northwest, Amazon, and Kairos Power, current through 17 Oct 2026 (opens the source)
- FilingTalen SEC confirmation of the Susquehanna front-of-meter transitionTalen Energy · Form 10-Q filed with the US Securities and Exchange Commission, 2026 (opens the source)
- ResearchDOE large-load rate design and integrated-resource-planning frameworkUS Department of Energy / Lawrence Berkeley National Laboratory · 2024-2025 (opens the source)
- CompanySpaceXAI Greater Memphis Area updateSpaceXAI · 30 Jul 2026 (opens the source)
- CompanyIntersect current solutions and acquisition statusIntersect · current through 2026 (opens the source)
- CompanyOracle Project Jupiter fuel-cell planOracle · 27 Apr 2026 through 15 Oct 2026 (opens the source)
- CompanyEntergy/Meta Richland Parish generationEntergy Louisiana · 6 Dec 2024 and 20 Aug 2025; Entergy 2025 Performance Report published 2026 (opens the source)
- CompanyMeta/Constellation Clinton agreementMeta · 3 Jun 2025 (opens the source)
- CompanyGoogle/Kairos/TVA Hermes 2Google · 18 Aug 2025 (opens the source)
- CompanyAmazon/X-energy/Energy NorthwestAmazon · 16 Oct 2024 with later updates (opens the source)
- CompanyGoogle/Elementl Power site developmentGoogle · 7 May 2025 (opens the source)
- CompanyMeta nuclear agreements with Vistra, TerraPower, and OkloMeta · 9 Jan 2026 (opens the source)
- CompanyAlphabet/Intersect acquisition and IPX asset boundaryAlphabet SEC filing and Intersect/IPX transaction records · 2026 (opens the source)
- SourcePPA and project-finance risk frameworkUS Department of Energy and National Renewable Energy Laboratory · 2024-current (opens the source)
“And who carries the risk if construction runs late, costs explode, or the customer disappears?”
As checked: Large-load utility tariffs and negotiated service agreements can allocate generation, transmission, interconnection, minimum-payment, exit, and stranded-asset risk differently between the large customer and other ratepayers.
- RegulatorLPSC final Meta/Entergy order and customer-protection termsLouisiana Public Service Commission · Order U-37425 decided 20 Aug 2025 (opens the source)
- ResearchDOE large-load rate design and integrated-resource-planning frameworkUS Department of Energy / Lawrence Berkeley National Laboratory · 2024-2025 (opens the source)
“And who carries the risk if construction runs late, costs explode, or the customer disappears?”
As checked: Long-term PPAs, offtake rights, equity investment, and development funding can improve project financeability by reallocating revenue and development risk, but do not guarantee completion or remove schedule, technology, fuel, construction, and regulatory risk.
“It can finance a project before committing to its output. It can place computers beside an existing plant. Or it can pay a utility that builds generation for the wider system.”
As checked: Entergy's first approved Meta-related Louisiana package contains three combined-cycle plants totaling about 2,260 MW; Entergy later announced plans for seven additional plants totaling more than 5,200 MW under a separate expansion agreement. Meta does not own the plants.
- RegulatorLPSC final Meta/Entergy order and customer-protection termsLouisiana Public Service Commission · Order U-37425 decided 20 Aug 2025 (opens the source)
- CompanyEntergy/Meta Richland Parish generationEntergy Louisiana · 6 Dec 2024 and 20 Aug 2025; Entergy 2025 Performance Report published 2026 (opens the source)
- CompanyEntergy/Meta second Louisiana infrastructure announcementEntergy Louisiana · 27 Mar 2026 (opens the source)
Also used in this chapter
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- RegulatorMicrosoft/Constellation Crane restartConstellation and US Nuclear Regulatory Commission · 2024-2026 (opens the source)
- RegulatorAmazon/Talen Susquehanna co-location recordUS Federal Energy Regulatory Commission and federal court filing · 2024-2025 (opens the source)
- RegulatorCurrent status refresh for planned nuclear examplesUS Nuclear Regulatory Commission · Energy Northwest, Amazon, and Kairos Power, current through 17 Oct 2026 (opens the source)
- FilingTalen SEC confirmation of the Susquehanna front-of-meter transitionTalen Energy · Form 10-Q filed with the US Securities and Exchange Commission, 2026 (opens the source)
- CompanySpaceXAI Greater Memphis Area updateSpaceXAI · 30 Jul 2026 (opens the source)
- CompanySpaceX AI-segment corporate and public-brand refreshSpaceX SEC filing and SpaceXSI legal/site materials · current through 17 Oct 2026 (opens the source)
- CompanyIntersect current solutions and acquisition statusIntersect · current through 2026 (opens the source)
- CompanyAmazon/X-energy/Energy NorthwestAmazon · 16 Oct 2024 with later updates (opens the source)
- CompanyAlphabet/Intersect acquisition and IPX asset boundaryAlphabet SEC filing and Intersect/IPX transaction records · 2026 (opens the source)
This chapter states no new facts of its own.
Also used in this chapter
- RegulatorMicrosoft/Constellation Crane restartConstellation and US Nuclear Regulatory Commission · 2024-2026 (opens the source)
- RegulatorCurrent status refresh for planned nuclear examplesUS Nuclear Regulatory Commission · Energy Northwest, Amazon, and Kairos Power, current through 17 Oct 2026 (opens the source)
- CompanyAmazon/X-energy/Energy NorthwestAmazon · 16 Oct 2024 with later updates (opens the source)
- SourcePPA and project-finance risk frameworkUS Department of Energy and National Renewable Energy Laboratory · 2024-current (opens the source)
“So companies climbed another rung.”
As checked: On-site generation can reduce dependence on grid-delivery timing while creating or reallocating capital, permitting, emissions, fuel, redundancy, operating, and community-impact obligations among the site and its project partners.
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- RegulatorProject Jupiter New Mexico permit and court recordNew Mexico Environment Department and Supreme Court of New Mexico · current through 17 Oct 2026 (opens the source)
- RegulatorDOE and EPA framework for onsite generation and microgridsUS Department of Energy and US Environmental Protection Agency · current through 2026 (opens the source)
Also used in this chapter
- RegulatorAmazon/Talen Susquehanna co-location recordUS Federal Energy Regulatory Commission and federal court filing · 2024-2025 (opens the source)
- FilingTalen SEC confirmation of the Susquehanna front-of-meter transitionTalen Energy · Form 10-Q filed with the US Securities and Exchange Commission, 2026 (opens the source)
“In New Mexico, Oracle is pursuing that idea at utility scale.”
As checked: Oracle's Project Jupiter plans a behind-the-meter fuel-cell microgrid of up to 2.45 GW, with Oracle paying the project's energy costs.
Also used in this chapter
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- RegulatorDOE and EPA framework for onsite generation and microgridsUS Department of Energy and US Environmental Protection Agency · current through 2026 (opens the source)
- CompanySpaceXAI Greater Memphis Area updateSpaceXAI · 30 Jul 2026 (opens the source)
- CompanySpaceX AI-segment corporate and public-brand refreshSpaceX SEC filing and SpaceXSI legal/site materials · current through 17 Oct 2026 (opens the source)
- CompanyIntersect current solutions and acquisition statusIntersect · current through 2026 (opens the source)
- CompanyAlphabet/Intersect acquisition and IPX asset boundaryAlphabet SEC filing and Intersect/IPX transaction records · 2026 (opens the source)
This chapter states no new facts of its own.
Also used in this chapter
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- RegulatorMicrosoft/Constellation Crane restartConstellation and US Nuclear Regulatory Commission · 2024-2026 (opens the source)
- RegulatorAmazon/Talen Susquehanna co-location recordUS Federal Energy Regulatory Commission and federal court filing · 2024-2025 (opens the source)
- RegulatorProject Jupiter New Mexico permit and court recordNew Mexico Environment Department and Supreme Court of New Mexico · current through 17 Oct 2026 (opens the source)
- RegulatorLPSC final Meta/Entergy order and customer-protection termsLouisiana Public Service Commission · Order U-37425 decided 20 Aug 2025 (opens the source)
- RegulatorDOE and EPA framework for onsite generation and microgridsUS Department of Energy and US Environmental Protection Agency · current through 2026 (opens the source)
- RegulatorCurrent status refresh for planned nuclear examplesUS Nuclear Regulatory Commission · Energy Northwest, Amazon, and Kairos Power, current through 17 Oct 2026 (opens the source)
- FilingTalen SEC confirmation of the Susquehanna front-of-meter transitionTalen Energy · Form 10-Q filed with the US Securities and Exchange Commission, 2026 (opens the source)
- ResearchKey Questions on Energy and AIInternational Energy Agency · 2026 (opens the source)
- ResearchDOE large-load rate design and integrated-resource-planning frameworkUS Department of Energy / Lawrence Berkeley National Laboratory · 2024-2025 (opens the source)
- CompanySpaceXAI Greater Memphis Area updateSpaceXAI · 30 Jul 2026 (opens the source)
- CompanyIntersect current solutions and acquisition statusIntersect · current through 2026 (opens the source)
- CompanyOracle Project Jupiter fuel-cell planOracle · 27 Apr 2026 through 15 Oct 2026 (opens the source)
- CompanyEntergy/Meta Richland Parish generationEntergy Louisiana · 6 Dec 2024 and 20 Aug 2025; Entergy 2025 Performance Report published 2026 (opens the source)
- CompanyMeta/Constellation Clinton agreementMeta · 3 Jun 2025 (opens the source)
- CompanyGoogle/Kairos/TVA Hermes 2Google · 18 Aug 2025 (opens the source)
- CompanyAmazon/X-energy/Energy NorthwestAmazon · 16 Oct 2024 with later updates (opens the source)
- CompanyGoogle/Elementl Power site developmentGoogle · 7 May 2025 (opens the source)
- CompanyMeta nuclear agreements with Vistra, TerraPower, and OkloMeta · 9 Jan 2026 (opens the source)
- CompanyAlphabet/Intersect acquisition and IPX asset boundaryAlphabet SEC filing and Intersect/IPX transaction records · 2026 (opens the source)
- CompanyEntergy/Meta second Louisiana infrastructure announcementEntergy Louisiana · 27 Mar 2026 (opens the source)
- SourcePPA and project-finance risk frameworkUS Department of Energy and National Renewable Energy Laboratory · 2024-current (opens the source)
This chapter states no new facts of its own.
Also used in this chapter
- RegulatorLPSC final Meta/Entergy order and customer-protection termsLouisiana Public Service Commission · Order U-37425 decided 20 Aug 2025 (opens the source)
- ResearchDOE large-load rate design and integrated-resource-planning frameworkUS Department of Energy / Lawrence Berkeley National Laboratory · 2024-2025 (opens the source)
- CompanyEntergy/Meta Richland Parish generationEntergy Louisiana · 6 Dec 2024 and 20 Aug 2025; Entergy 2025 Performance Report published 2026 (opens the source)
- CompanyEntergy/Meta second Louisiana infrastructure announcementEntergy Louisiana · 27 Mar 2026 (opens the source)
This chapter states no new facts of its own.
Also used in this chapter
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- RegulatorProject Jupiter New Mexico permit and court recordNew Mexico Environment Department and Supreme Court of New Mexico · current through 17 Oct 2026 (opens the source)
- RegulatorLPSC final Meta/Entergy order and customer-protection termsLouisiana Public Service Commission · Order U-37425 decided 20 Aug 2025 (opens the source)
- RegulatorDOE and EPA framework for onsite generation and microgridsUS Department of Energy and US Environmental Protection Agency · current through 2026 (opens the source)
- ResearchDOE large-load rate design and integrated-resource-planning frameworkUS Department of Energy / Lawrence Berkeley National Laboratory · 2024-2025 (opens the source)
- SourcePPA and project-finance risk frameworkUS Department of Energy and National Renewable Energy Laboratory · 2024-current (opens the source)
This chapter states no new facts of its own.
Also used in this chapter
- RegulatorSouthaven permit, corporate structure, and temporary-turbine recordMississippi Department of Environmental Quality · US Securities and Exchange Commission, US Department of Justice, and SpaceXAI, current through 17 Oct 2026 (opens the source)
- RegulatorMicrosoft/Constellation Crane restartConstellation and US Nuclear Regulatory Commission · 2024-2026 (opens the source)
- RegulatorAmazon/Talen Susquehanna co-location recordUS Federal Energy Regulatory Commission and federal court filing · 2024-2025 (opens the source)
- RegulatorProject Jupiter New Mexico permit and court recordNew Mexico Environment Department and Supreme Court of New Mexico · current through 17 Oct 2026 (opens the source)
- RegulatorLPSC final Meta/Entergy order and customer-protection termsLouisiana Public Service Commission · Order U-37425 decided 20 Aug 2025 (opens the source)
- RegulatorDOE and EPA framework for onsite generation and microgridsUS Department of Energy and US Environmental Protection Agency · current through 2026 (opens the source)
- RegulatorCurrent status refresh for planned nuclear examplesUS Nuclear Regulatory Commission · Energy Northwest, Amazon, and Kairos Power, current through 17 Oct 2026 (opens the source)
- FilingTalen SEC confirmation of the Susquehanna front-of-meter transitionTalen Energy · Form 10-Q filed with the US Securities and Exchange Commission, 2026 (opens the source)
- ResearchKey Questions on Energy and AIInternational Energy Agency · 2026 (opens the source)
- ResearchDOE large-load rate design and integrated-resource-planning frameworkUS Department of Energy / Lawrence Berkeley National Laboratory · 2024-2025 (opens the source)
- CompanySpaceXAI Greater Memphis Area updateSpaceXAI · 30 Jul 2026 (opens the source)
- CompanySpaceX AI-segment corporate and public-brand refreshSpaceX SEC filing and SpaceXSI legal/site materials · current through 17 Oct 2026 (opens the source)
- CompanyIntersect current solutions and acquisition statusIntersect · current through 2026 (opens the source)
- CompanyOracle Project Jupiter fuel-cell planOracle · 27 Apr 2026 through 15 Oct 2026 (opens the source)
- CompanyEntergy/Meta Richland Parish generationEntergy Louisiana · 6 Dec 2024 and 20 Aug 2025; Entergy 2025 Performance Report published 2026 (opens the source)
- CompanyMeta/Constellation Clinton agreementMeta · 3 Jun 2025 (opens the source)
- CompanyGoogle/Kairos/TVA Hermes 2Google · 18 Aug 2025 (opens the source)
- CompanyAmazon/X-energy/Energy NorthwestAmazon · 16 Oct 2024 with later updates (opens the source)
- CompanyGoogle/Elementl Power site developmentGoogle · 7 May 2025 (opens the source)
- CompanyMeta nuclear agreements with Vistra, TerraPower, and OkloMeta · 9 Jan 2026 (opens the source)
- CompanyAlphabet/Intersect acquisition and IPX asset boundaryAlphabet SEC filing and Intersect/IPX transaction records · 2026 (opens the source)
- SourcePPA and project-finance risk frameworkUS Department of Energy and National Renewable Energy Laboratory · 2024-current (opens the source)
What you are seeing
Every scene of the film is one of four kinds, and the picture always says which.
- evidence
Real evidence
A documented fact, attributed and dated: a regulator, a record or a company says.
- illustrated
Reconstruction
A real case redrawn in our style: no logos, no real buildings.
- explanation
Explanation
The idea itself, drawn with our own pictures.
- scenario
Scenario
A possible future: always labelled, never shown as fact.
Real evidence · 18
- State records name MZX Tech LLC as the permit holder.…
- SpaceXSI says the project will contain forty-one turbines and produce…
- The permit authorizes construction; it does not mean the plant…
- US data centers used about 192 terawatt-hours of electricity in…
- Microsoft has agreed to buy power under a twenty-year contract.
- Talen says the transition to a front-of-the-meter agreement occurred in…
- Oracle says it will bear the energy costs.
- But the word “own” remains slippery. Bloom supplies the fuel…
- New Mexico listed air permit 10883 as pending on October…
- Google did.
- The transaction included Intersect's team and multiple gigawatts of energy…
- But even here, the footnotes matter. IPX Power was carved…
- State regulators approved it in 2025.
- For Louisiana's first approved Meta package, the settlement includes protections.
- Entergy must obtain parent guarantees and collateral.
- Early departure triggers a termination fee, and the commission reviews…
- Material project-only transmission upgrades stay off other customers' rates.
- Entergy must report construction, and regulators can review the costs.
Reconstruction · 22
- In Southaven, Mississippi, SpaceX's AI division—now branded SpaceXSI—says it is…
- A power plant.
- That is power-station scale—being built to help feed computers. Hungry…
- Public records do not reveal who legally owns every turbine.
- Start with the promise.
- Microsoft does not own the reactor. Constellation does. And the…
- Amazon is using a different lever in Washington State. It…
- Yet Energy Northwest—not Amazon—is expected to construct, own, and operate…
- Even that description is ahead of the machinery. The project…
- That is the logic behind Amazon's campus beside Pennsylvania's Susquehanna…
- Except the reactor belongs to Talen, not Amazon.
- In New Mexico, Oracle is pursuing that idea at utility…
- Project Jupiter's plan proposes up to 2.45 gigawatts of Bloom…
- Public documents do not establish that Oracle owns the generating…
- And this is still a proposal moving through regulation, not…
- This was not merely a contract for electricity. Google bought…
- In Louisiana, Meta chose the utility route.
- Its Hyperion data-center campus led Entergy Louisiana to an initial…
- Entergy began construction that December on two Richland Parish plants;…
- Then the scale grew. In March 2026, Entergy announced plans…
- Meta did not become a power company. It became a…
- Return to Southaven.
Explanation · 70
- Not a chip factory. Not a model.
- But the category collision is real. A software business is…
- And it is not alone.
- Technology companies are signing decades-long power contracts, financing reactors, placing…
- They are not all building their own plants. They are…
- Why would a technology company wander into the energy business?
- Because an AI data center runs on two different clocks.
- On the digital clock, models improve, capital moves, and campuses…
- On the electrical clock, utilities must approve projects, secure permits,…
- Those clocks are drifting apart. And you cannot download a…
- It is a projection, not a promise—and includes every kind…
- But the pressure is concentrated. A giant campus does not…
- The industry calls the problem time-to-power: how long until dependable…
- If the answer is later than the data center, companies…
- Wait for the grid—
- The word “own” sounds simple until electricity gets involved.
- The plug becomes a meter. The meter becomes a utility…
- So ask three separate questions.
- Where is that machine—beside the data center, across the grid,…
- And who carries the risk if construction runs late, costs…
- Those questions create six arrangements. A technology company can buy…
- It can finance a project before committing to its output.…
- One project can use several at once.
- Think of them as a ladder of control. The first…
- It begins with a promise: if you build the power,…
- But Microsoft's commitment matters because power projects consume money long…
- Developers must finance engineering, equipment, construction, and fuel.
- A long-term buyer makes future revenue less mysterious. It gives…
- So a technology company can influence which power plants return…
- A contract controls future output. Early capital buys influence and…
- But there is another shortcut that looks almost comically obvious.
- From above, the arrangement looks like the world's most expensive…
- And being neighbors did not make the data center a…
- The original arrangement placed the campus behind the meter.
- When a proposed expansion ran into federal regulatory resistance, Amazon…
- In plain English, the data center remained beside the plant,…
- Nothing important moved on the map. Almost everything important changed…
- That is why co-location is not ownership, and “beside a…
- Geography can reduce some transmission and scheduling friction, but regulators,…
- So companies climbed another rung.
- Behind the meter does not mean off-grid. A microgrid can…
- Oracle's fuel cells and Southaven's turbines are different technologies. Their…
- But every shortcut brings its own homework—capital, permits, fuel, maintenance,…
- To gain more control, a company can keep assembling partners.
- That sounds like the top of the control ladder—and at…
- So “Google bought Intersect” does not mean “Google owns every…
- What Google unquestionably acquired was capability: people, projects, expertise, and…
- That is when “moving into the power business” becomes literal.…
- Yet buying an energy developer is expensive, unusual, and unnecessary…
- They were proposals, not part of the 2025 approval.
- That is the difference between cause and ownership.
- For Meta, the arrangement summons gigawatts without operating turbines. For…
- But utility assets can outlive contracts. Forecasts can be wrong.…
- So the final question is not who owns the plant.
- Every rung on the control ladder moves risk. None makes…
- Long contracts stabilize revenue, but bind buyers.
- Development capital can launch a reactor project, but cannot manufacture…
- On-site generation reduces dependence on grid timing, then creates obligations…
- Utility construction moves risk into public regulation.
- But the generators remain utility system resources. Eligible costs can…
- And money is only one ledger. Depending on the technology…
- Speed has a price.
- Most companies do not need a power-plant deed. They need…
- That confidence can come from contracts, finance, co-location, on-site generation,…
- Chips and models are no longer the entire AI stack.…
- Software's trick is abstraction: hide machinery and make complexity feel…
- It must be generated somewhere, carried through something, approved by…
- So AI companies are not all building their own power…
- They are moving into the power business because advantage may…
- The prize is not simply owning the plant.
Scenario · 3
- Because the best computer in the world is still useless…
- Picture a server plugged into a power plant. Now pull…
- If the electricity cannot reach the computer quickly enough, move…
Transcript
0 · A power plant for a computer
- In Southaven, Mississippi, SpaceX's AI division—now branded SpaceXSI—says it is building something that looks nothing like AI.
- Not a chip factory. Not a model.
- A power plant.
- State records name MZX Tech LLC as the permit holder. Federal records place it inside SpaceX's AI business.
- SpaceXSI says the project will contain forty-one turbines and produce 1.2 gigawatts.
- That is power-station scale—being built to help feed computers. Hungry computers.
- The permit authorizes construction; it does not mean the plant is already operating.
- Public records do not reveal who legally owns every turbine.
- But the category collision is real. A software business is reaching backward into fuel, steel, permits, and generation.
- And it is not alone.
- Technology companies are signing decades-long power contracts, financing reactors, placing data centers beside power stations, and even buying energy developers.
- They are not all building their own plants. They are buying control over when electricity becomes available.
- Because the best computer in the world is still useless if its power arrives years late.
1 · The two clocks
- Why would a technology company wander into the energy business?
- Because an AI data center runs on two different clocks.
- On the digital clock, models improve, capital moves, and campuses rise quickly.
- On the electrical clock, utilities must approve projects, secure permits, order equipment, build lines and substations, then test everything before the first rack draws power.
- Those clocks are drifting apart. And you cannot download a substation.
- US data centers used about 192 terawatt-hours of electricity in 2024. In the Department of Energy's reference case, that rises to 649 terawatt-hours by 2030.
- It is a projection, not a promise—and includes every kind of data center, not AI alone.
- But the pressure is concentrated. A giant campus does not ask the country for a little electricity. It asks one region for a block, on one date.
- The industry calls the problem time-to-power: how long until dependable electricity is available where the computers will stand?
- If the answer is later than the data center, companies have two choices.
- Wait for the grid—
2 · "Their own" is doing too much work
- The word “own” sounds simple until electricity gets involved.
- Picture a server plugged into a power plant. Now pull on the cable.
- The plug becomes a meter. The meter becomes a utility tariff. Behind that sit transmission lines, permits, fuel contracts, lenders, and agreements. It is a very long cable.
- So ask three separate questions.
- Where is that machine—beside the data center, across the grid, or still on a drawing board?
- And who carries the risk if construction runs late, costs explode, or the customer disappears?
- Those questions create six arrangements. A technology company can buy an energy developer. It can host generation on-site. It can promise to buy electricity through a long-term power purchase agreement.
- It can finance a project before committing to its output. It can place computers beside an existing plant. Or it can pay a utility that builds generation for the wider system.
- One project can use several at once.
- Think of them as a ladder of control. The first rung requires no turbine, reactor, or smokestack on a single technology company's balance sheet.
- It begins with a promise: if you build the power, we will buy it for decades.
3 · Buy twenty years of tomorrow
- Start with the promise.
- Microsoft has agreed to buy power under a twenty-year contract.
- Microsoft does not own the reactor. Constellation does. And the plant is not operating yet; the restart remains under federal review.
- But Microsoft's commitment matters because power projects consume money long before they produce electricity.
- Developers must finance engineering, equipment, construction, and fuel.
- A long-term buyer makes future revenue less mysterious. It gives lenders and investors something to model.
- Amazon is using a different lever in Washington State. It invested in reactor developer X-energy and is helping advance a first 320-megawatt project with Energy Northwest.
- Yet Energy Northwest—not Amazon—is expected to construct, own, and operate the reactors.
- Even that description is ahead of the machinery. The project remains in feasibility, design, and due diligence, with a Nuclear Regulatory Commission construction-permit application still to come.
- So a technology company can influence which power plants return or get developed without owning the steel.
- A contract controls future output. Early capital buys influence and options.
- But there is another shortcut that looks almost comically obvious.
- If the electricity cannot reach the computer quickly enough, move the computer next to the electricity source. Every cat knows this trick. If the warm spot won't come to you, go to the warm spot.
4 · Move the computer to the power
- That is the logic behind Amazon's campus beside Pennsylvania's Susquehanna nuclear station.
- From above, the arrangement looks like the world's most expensive extension cord: reactor here, data center there, problem solved.
- Except the reactor belongs to Talen, not Amazon.
- And being neighbors did not make the data center a private grid island.
- The original arrangement placed the campus behind the meter.
- When a proposed expansion ran into federal regulatory resistance, Amazon and Talen rewrote the structure.
- Talen says the transition to a front-of-the-meter agreement occurred in April 2026.
- In plain English, the data center remained beside the plant, but its commercial and electrical relationship moved through the grid-facing side of the meter.
- Nothing important moved on the map. Almost everything important changed on paper.
- That is why co-location is not ownership, and “beside a power plant” does not mean “plugged directly into a private reactor.”
- Geography can reduce some transmission and scheduling friction, but regulators, markets, and grid rules still exist between the machines.
- So companies climbed another rung.
5 · Move the power to the computer
- In New Mexico, Oracle is pursuing that idea at utility scale.
- Project Jupiter's plan proposes up to 2.45 gigawatts of Bloom Energy fuel cells in a behind-the-meter microgrid for its data-center campus.
- Oracle says it will bear the energy costs.
- But the word “own” remains slippery. Bloom supplies the fuel cells. Yucca Growth Infrastructure and BorderPlex are development partners.
- Public documents do not establish that Oracle owns the generating assets.
- And this is still a proposal moving through regulation, not 2.45 gigawatts humming in the desert.
- New Mexico listed air permit 10883 as pending on October 17, 2026. A temporary court stay was lifted in September, but no final permit had appeared.
- Behind the meter does not mean off-grid. A microgrid can interact with the wider grid, operate independently in some conditions, or combine both modes, depending on its design.
- Oracle's fuel cells and Southaven's turbines are different technologies. Their strategic logic is similar: reduce dependence on the grid's delivery timetable.
- But every shortcut brings its own homework—capital, permits, fuel, maintenance, redundancy, emissions rules, and local impacts. And nobody gets to copy the answers.
- To gain more control, a company can keep assembling partners.
6 · Buy the company that builds the power
- Google did.
- This was not merely a contract for electricity. Google bought the organization that assembles sites, permits, capital, and generation around data-center construction.
- The transaction included Intersect's team and multiple gigawatts of energy and data-center projects in development or construction.
- That sounds like the top of the control ladder—and at the developer level, it is.
- But even here, the footnotes matter. IPX Power was carved out during the sale, retaining a large portfolio of solar and battery assets in Texas and California.
- So “Google bought Intersect” does not mean “Google owns every power plant Intersect ever developed.” Owning the developer also does not reveal who holds title to every generator.
- What Google unquestionably acquired was capability: people, projects, expertise, and a development pipeline designed to make computing and energy arrive together.
- That is when “moving into the power business” becomes literal. No metaphor required.
- Yet buying an energy developer is expensive, unusual, and unnecessary for most companies if someone else can build the megawatts on schedule.
7 · Let the utility build it
- In Louisiana, Meta chose the utility route.
- Its Hyperion data-center campus led Entergy Louisiana to an initial package: three combined-cycle gas plants totaling about 2,260 megawatts, plus transmission infrastructure.
- State regulators approved it in 2025.
- Entergy began construction that December on two Richland Parish plants; a third is planned later for Waterford.
- Then the scale grew. In March 2026, Entergy announced plans for seven additional gas plants totaling more than 5,200 megawatts, plus transmission and batteries.
- They were proposals, not part of the 2025 approval.
- Meta did not become a power company. It became a very large customer. Entergy—not Meta—would build, own, and operate them, integrating them into its system. Meta pays through utility agreements.
- That is the difference between cause and ownership.
- For Meta, the arrangement summons gigawatts without operating turbines. For Entergy, it creates a customer and infrastructure for the broader grid.
- But utility assets can outlive contracts. Forecasts can be wrong. Eligible costs can enter regulated rates.
- So the final question is not who owns the plant.
8 · Who pays for speed?
- Every rung on the control ladder moves risk. None makes it disappear.
- Long contracts stabilize revenue, but bind buyers.
- Development capital can launch a reactor project, but cannot manufacture a license or a working plant.
- On-site generation reduces dependence on grid timing, then creates obligations for permits, fuel, maintenance, backup capacity, and community acceptance.
- Utility construction moves risk into public regulation.
- For Louisiana's first approved Meta package, the settlement includes protections.
- Entergy must obtain parent guarantees and collateral.
- Early departure triggers a termination fee, and the commission reviews how it is used.
- Material project-only transmission upgrades stay off other customers' rates.
- Entergy must report construction, and regulators can review the costs.
- But the generators remain utility system resources. Eligible costs can enter Entergy's rates. Protections reduce exposure, not all risk.
- And money is only one ledger. Depending on the technology and location, speed can bring emissions, water use, land demands, noise, fuel dependence—or new capacity and local investment for host communities.
- Speed has a price.
9 · The new AI moat
- Return to Southaven.
- Most companies do not need a power-plant deed. They need confidence that enough electricity will exist, in the right place, when their servers are ready.
- That confidence can come from contracts, finance, co-location, on-site generation, utility agreements, or acquired developers. Each controls part of the schedule.
- Chips and models are no longer the entire AI stack. Land, permits, fuel, generation, financing, and utility relationships are competitive infrastructure too.
- Software's trick is abstraction: hide machinery and make complexity feel instant.
- It must be generated somewhere, carried through something, approved by someone, and paid for by somebody.
- So AI companies are not all building their own power plants.
- They are moving into the power business because advantage may belong to whoever can make physical infrastructure meet a digital deadline.
- The prize is not simply owning the plant.
How this film was made
Researched, written, drawn and checked by our team. We use AI tools throughout: research, writing, code-drawn animation, narration and music. Every claim is linked to its source.
Corrections
No corrections to date.
Spotted an error? Write to [email protected] with the film's title.Spotted an error? Email us ↗